The major source of Sydney's water supply, Warragamba Dam, Australia's fourth
largest dam, was raised to its present height of 142 metres in 1989.
Its primary function is to provide a water supply for the Sydney Metropolitan area and when
adequate quantities of water are stored to meet these needs, electricity is generated
and fed into the NSW grid by the hydro-electric power station located at the base of
the dam. Warragamba dam is classified a 'Major Dam' under Australian National
Committee on Large Dams (ANCOLD) definitions and is in the High Incremental
Flood Hazard category.
To prevent overtopping, an auxiliary spillway is being constructed adjacent to the dam
to divert floodwaters in excess of the capacity of the existing spillway around the dam
wall. The combined spillway capacity (the existing central spillway plus auxiliary
spillway) will be sufficient to safely pass a Probable Maximum Flood (PMF).
The auxiliary spillway is a major civil engineering project due for completion in
mid-2001. It has been undertaken by the Sydney Water Corporation (now known as
the Sydney Catchment Authority) to improve the safety of the dam. The contract for
the design and engineering of the spillway was awarded to SMEC, the Snowy
Mountains Engineering Corporation.
The project involves major excavation - some 1.8 million cubic metres of sandstone is
being removed and transported to a soil emplacement- and the concrete lining of the
auxiliary chute spillway which will be approximately 650 metres long and drop 50
metres before discharging to the river.
The linings, and joints in linings within the spillway, have to be designed to withstand
spillway flows at very high velocity and the components must be capable of handling
considerable hydro-dynamic forces.
Five fuse plugs - embankments that wash away when overtopped - are being built
downstream of the inlet to prevent the auxiliary spillway from operating in flood flows
smaller than about a one in 750 chance of occurrence in any year. The fuse plugs are
constructed of rockfill, gravel and sand, with a clay core. Generally, the floor and wall
of the spillway chute are in the form of a reinforced concrete lining against the
excavated rock surface, however, one section of the spillway over an existing creek
line will be constructed on compacted fill with cantilever walls on either side.
A bridge across the spillway, and a new road, are designed to provide access to the
crest of the dam, valve house - which channels the water flow, and hydro-electric
power station at the base of the dam.
Following concept design carried out by the Department of Public Works and
Services, SMEC is responsible for the detail design development - from concept to
production of construction drawings.
4D Model was used for design and modelling of the auxiliary spillway and associated
access structures such as roads and the bridge approach, along with calculation of
spoil volumes. The spillway required comprehensive design work to achieve correct
water flow and required a number of design modifications in the dimensions of the
deflector walls and fuse plugs to achieve appropriate flow control.
The design had to be continually modified for volumes of spoil placement and slope
analysis to fit placement within specified confines nominated by the client. The spoil
would not fit into the area initially defined and required many modifications of the
design.
Reports of cut and fill areas and volumes were given on a section-by-section basis
plus colour coded depth volumes for validation and plots. Similarly the perspectives
provided using 4D were an easy way to convey a design to people who find
engineering plans and contours difficult to interpret.
SMEC is also using the 4D Drainage Module in the Warragamba project. This
supports the display of drainage networks typically required for development projects
and new land subdivisions.