Khalifa Ports and Industrial Zone
 
Project Summary
Khalifa Port and Industrial Zone Abu Dhabi is one of the world’s largest 
greenfield development projects as well as one of the world’s largest combined 
port and industrial zone developments. It is an integral part of Abu Dhabi’s 
vision of sustainable economic growth in the United Arab Emirates (UAE). The 
industrial zone is located almost equidistant to Abu Dhabi and Dubai, with 
extended frontage along the E11 Highway connecting the two cities.
Habtoor Leighton Group was proud to secure 
the project. Scope of work includes the onshore civil and building package for 
the Khalifa Port and Industrial Zone. As a design and construction project, the 
works included around 40 buildings ranging from single guard houses to the 
80,0000 square metre central facilities, to civil engineering infrastructure 
works such as 18km of 4 -and 6-lane expressway, 38 RCC culverts, 2 interchanges 
with entry and exit ramps, 2 railway bridges, and 11kV/33kV networking. Other 
utilities such as combined waste water, potable water, groundwater, stormwater, 
process water and services are also included, as are associated infrastructure 
works consisting of a series of road networks, bridges, utility installations, 
containment structures, reinforced earth embankments, patrol roads, an exterior 
maintenance system, MEP works, building detailing, signage, hard and soft 
landscaping, and maintenance.
 
The Challenge
This complex project involved design issues such as road top level clashes with 
existing utilities, bridges, culverts, and the deck top level. Most of the road 
profiles the team used were revised as per site condition. At the project’s 
outset, it seemed there would not even be enough time for them to design 
profiles and work out these issues before the milestone.
 
The Solution
With the help of 12d Model software, though, the Leighton team did achieve 
success in this project.
They raised the levels on the profile as 
necessary, edited super alignments by string, and changed the vertical 
intersection points from the vertical IP properties. They also input all the 
data such as IP chainages, vertical curve length, and ‘click to set’, by which 
12d Model automatically regenerated the vertical profile and automatically set 
the k values and radius as required, giving the ability to change the profile of 
roads as per the control line.
Next, they edited their design models and 
retriangulates TINs as per the new controls, then uploaded to the millimetre GPS 
in asphalt paver, by which they were able to smoothly pave asphalt with the 
required thickness above the concrete deck.
In addition to assisting design, 12d Model 
helped the team to minimise their required survey crew, as they did not need to 
fix any Line/Levels on the pavement work. Once they created models, they were 
able to upload these to the machines (graders, bull dozers, etc.) so that a 
single operator could finished the grading work both quantitatively and 
qualitatively.
12d Model also helped the 
team to prepare conformance reports, plotting the topographic survey in a short 
time and with attractive presentation.
 
The Result
The Leighton team found 12d Model to be a very efficient and useful software 
product to help them save a great deal of money by reducing manpower and time, 
and helping them finish their project ahead of schedule.
 
                                                            
                                                            Download this Case Study as a PDF
                                                                HERE